PROJECT : Construction, installation and fit out of a brand new café for Pret at Gatwick Airport Airside 3A
TIMESCALE : 5 WEEKS

Construction
Installation of new drylined walls and all wall finishes; tiled, wooden panels and painted. Installation of new vinyl flooring and altro flooring. New signage and branding installed.

Catering Install
Brand new servery counter area installed including a reconfiguration of the existing kitchen area and installation of new catering equipment.

Electrical & Plumbing
- Installation of new electrical system, lighting and all outlets. Installation and modifications to fire alarm system.
- Installation of new plumbing system