PROJECT : Front of House Refurbishment for the Zest Restaurant
TIMESCALE : 10 WEEKS
330c5d_9c4126ccbb054e2b9beea8ac28c5b5d6~mv2
Construction
  • Disassembled and disposed of the old counter
  • Installed new counter
  • Painted and decorated all interiors
330c5d_70b05435c00442c3a544e3b64c961cc6~mv2
Plumbing & Electrical
  • Disconnected and removed all existing equipment
  • Made necessary cold water supply alterations
  • Made necessary electrical and plumbing alterations to fit new equipment and brand new counter
  • Tested and commissioned all new installation works
  • Installed new lighting
  • Reworked supply of water and electrics
  • Installed all new equipment
330c5d_b8b077ce16d64ba18c45db21268c7aff~mv2
Planning
  • Obtained all permits required by Heathrow Airport (including the required Change Control approval)
  • Managed the project from conception to opening